DiMarco PA Cyber

The project involves the removal and disposal of existing asphalt, followed by cutting to subgrade, including the excavation of ponds and tanks. Fill material will be used to grade the site, preparing it for further development. Additionally, underground detention tank systems will be installed to manage stormwater runoff. The scope of work also includes the installation of sanitary, water, and gas utilities to service the site, ensuring all infrastructure needs are met for the successful completion of the project.